265, 277, 281, 287, 2871/2 Elm St - Site Plan Review

pending

Gallery

Auto-selected pages from the source documents. See Documents on file below for the originals.

Project details

What is proposed

The applicant proposes a residential community called "Rocky Hill" on multiple Elm Street parcels under the Rocky Hill Multi‑Family Overlay District (RH‑MFOD). The Site Plan Review submission shows 381 residential units: a South Neighborhood of 85 for‑sale homes (single‑family, duplex, triplex and four‑plex buildings) and a North Neighborhood of 296 rental units arranged in 29 apartment buildings. Ten percent (10%) of units are designated as Affordable Housing under the RH‑MFOD.

The proposal includes community buildings and a range of on‑site amenities: a clubhouse, pool, recreation/fieldhouse, pickleball courts, a dog park, formal greens, pocket parks, and an interconnected network of sidewalks and trails.

Where and how big

The site plan materials describe development on an approximately 65‑acre site comprised of six tax parcels on the east side of Elm Street. The Transportation Impact Assessment (prepared for the MEPA filing) references the development study area as roughly 87.4± acres; the Site Plan Review packet and supporting plans show the buildings and internal roadway layout on the parcels identified in the application. The main entry is a boulevard from Elm Street that becomes a roundabout separating the South and North neighborhoods; most internal streets and common areas are proposed to remain private, while the boulevard segment is proposed for dedication as a public road.

Buildings in the South Neighborhood emphasize front‑facing porches and rear‑loaded garages; the North Neighborhood is configured as separate low‑rise apartment buildings around a village green and amenity campus.

Parking, access and transportation

Primary vehicular access is a single full‑access driveway to Elm Street opposite the Hampton Inn entrance. A secondary, gated emergency access is shown via an existing easement through the adjacent Amesbury Animal Hospital property. The site plans locate most resident parking behind buildings or in garages for the South Neighborhood and in surface/on‑street parking for the North Neighborhood; guest and public trailhead parking is also shown (including seven trailhead spaces near the roundabout).

Reported parking ratios are 2.87 spaces per residence in the South Neighborhood and 1.68 spaces per residence in the North Neighborhood. The Transportation Impact Assessment (TIA) references a targeted parking supply of 1.5 spaces per multifamily unit.

The TIA (Vanasse & Associates) estimates the project would generate approximately 2,738 weekday vehicle trips (24‑hour), with about 163 AM‑peak and 208 PM‑peak vehicle trips using Institute of Transportation Engineers rates. To address existing and project‑related impacts the applicant has committed to a set of mitigation measures in the submission, including: coordinated signal timing along Route 110, geometric improvements on Route 110 (including added through capacity westbound), an Interchange Improvement Study and MassWorks grant pursuit for the I‑95/Route 110 interchange, installation of a Rectangular Rapid Flashing Beacon (RRFB) at an Elm Street crossing (a pedestrian‑activated flashing crossing aid), Road Safety Audits (RSAs) at identified high‑crash intersections (an independent safety review to identify short‑term improvements), a Traffic Monitoring Program with periodic post‑occupancy counts and surveys, and Transportation Demand Management measures (designation of a transportation coordinator, rideshare matching, resident information, bicycle parking, and coordination with the regional transit provider on a potential bus stop and shelter).

Open space, environmental controls and other technical items

The plans preserve wooded perimeter areas and show trails for both residents and public access; conservation easements and deed restrictions are referenced to protect wetlands, stream corridors and other sensitive areas. The applicant’s materials state that all proposed structures meet or exceed the 25‑foot wetland setback required by the Amesbury Wetlands Protection Ordinance.

Multiple stormwater reports and drainage plans accompany the application and describe detention basins, best management practices and O&M provisions intended to meet local and state stormwater and erosion‑control requirements. Utilities are shown underground. Site lighting specifications in the submission indicate parking lights not to exceed 18 feet and walkway/driveway lighting not to exceed 12 feet.

Status and next steps

The Site Plan Review application was filed August 11, 2025. The project record includes the site plans and landscape plans, stormwater and drainage reports, the Transportation Impact Assessment (part of the MEPA DEIR/FEIR work), geotechnical and peer review responses, and Operation & Maintenance manuals. The applicant has participated in Technical Review Committee and Design Review Committee meetings and exchanged multiple technical peer review memos and responses with City staff and consultants.

Permits and approvals identified in the filing include local Site Plan Review, Definitive Subdivision, a Stormwater Permit, Wetlands Notice of Intent / Order of Conditions, and required MassDOT highway access approvals for Elm Street and any Route 110/I‑95 improvements. The application materials include specific mitigation commitments and a traffic monitoring program tied to Certificates of Occupancy and phased implementation, subject to receipt of necessary rights, permits and approvals.

Discussion at meetings

September 14, 2026PLANNING BOARD
Continued Public Hearing
Continued public hearing for Site Plan (Section XI.V) and Definitive Subdivision for the Rocky Hill development. Request to continue to September 28, 2026.
  • CONTINUE
    Continue both the Site Plan and Definitive Subdivision hearings for the Rocky Hill development (Rocky Hill Elm Street parcels) to September 28, 2026.
    Approved 7-0
August 24, 2026PLANNING BOARD
New Public Hearing
Definitive subdivision review for the Rocky Hill Development on multiple Elm Street parcels (265 R, 277 R, 281, 287, 287 R, 287.5 Elm Street); scheduled 2026-08-24.
  • CONTINUE
    Continue the Rocky Hill Development public hearings (site plan and definitive subdivision for parcels at 265R, 277R, 281, 287, 287R, 287.5 Elm Street) to the Planning Board meeting of September 14, 2026.
    Approved 4-0
August 10, 2026PLANNING BOARD
Continued Public Hearing
Site plan (Section XI.V) for the Rocky Hill Development at 265 R, 277 R, 281, 287, 287 R, 287.5 Elm Street; public hearing opened 2025-09-22. Request to continue to 2026-08-24.
  • OTHER
    Ask staff to begin drafting a decision for the Rocky Hill Development
    Approved unanimously
July 27, 2026PLANNING BOARD
Continued Public Hearing
Continued public hearing for Site Plan review (Section XI.V) for the Rocky Hill Development covering multiple Elm Street parcels.
July 13, 2026PLANNING BOARD
Continued Public Hearing
Continued public hearing (first heard 9-22-25) for Site Plan review under Section XI.V for the Rocky Hill Development at multiple Elm Street parcels.
  • CONTINUE
    Continue the continued public hearing and review for the Rocky Hill Development (Elm Street parcels) to the July 27, 2026 Planning Board meeting.
    Approved 7-0
June 8, 2026PLANNING BOARD
Continued Public Hearing
Site Plan review under Section XI.V for the Rocky Hill development. (Public hearing opened 9-22-25) Request to continue to July 13, 2026.
May 11, 2026PLANNING BOARD
Continued Public Hearing
Continued public hearing for Site Plan review under Section XI.V for the Rocky Hill development on Elm Street (265R, 277R, 281, 287, 287R, 287.5 Elm Street).
  • CONTINUE
    to continue Rocky Hill development to the June 8th meeting
    Approved 6-0
April 27, 2026PLANNING BOARD
Continued Public Hearing
Rocky Hill Development covering parcels 265 R, 277 R, 281, 287, 287 R, 287.5 Elm Street; Site Plan (Section XI.V). Original public hearing 9-22-25. Request to continue to May 11, 2026.
April 13, 2026PLANNING BOARD
Continued Public Hearing
Continued site plan review (Section XI.V) for the Rocky Hill Development covering parcels at 265 R, 277 R, 281, 287, 287 R, 287.5 Elm Street; request to continue to 4/27/26. (PH 9-22-25)
March 9, 2026PLANNING BOARD
Continued Public Hearing
Continued public hearing for Site Plan (Section XI.V) review for the Rocky Hill Development at 265 R, 277 R, 281, 287, 287 R, 287.5 Elm Street.
  • CONTINUE
    motion by Keith second by Joel to continue Rocky Hill to April 13th
    Approved 7-0
February 23, 2026PLANNING BOARD
Continued Public Hearing
Site Plan review under Section XI.V for the Rocky Hill development (multiple Elm Street parcels); public hearing originally opened 9-22-25.
January 29, 2026PLANNING BOARD
Continued Public Hearing
Continued review of Site Plan for the Rocky Hill development (265 R, 277 R, 281, 287, 287 R, 287.5 Elm Street) — Section XI.V; item includes a request to continue to 2026-02-23 (original hearing 9-22-25).
  • CONTINUE
    I'll make a motion 265 our 277 our 281 287 287 our 287 and a half Elm Street the rocky hill development we continue to February 23rd
    Approved 7-0
January 26, 2026PLANNING BOARD
Continued Public Hearing
Continued Site Plan review for the Rocky Hill development covering multiple Elm Street parcels; includes review under Section XI.V (MBTA Communities Multi‑family Overlay District).
December 22, 2025PLANNING BOARD
Continued Public Hearing
Site Plan review for Rocky Hill Development covering 265 R, 277 R, 281, 287, 287 R, 287.5 Elm Street. Public hearing originally 9-22-25. Request to continue to 1/26/25.
  • CONTINUE
    to continue site plan 26 are 27 to 7 to 65 are 277 are 281 287 and the rest of those rocky hill development until the meeting of january 26 20 26 actually
    Motion passes unanimously.
November 10, 2025PLANNING BOARD
Continued Public Hearing
Continued public hearing for Rocky Hill Development (265 R, 277 R, 281, 287, 287 R, 287.5 Elm Street) — Site Plan review under Section XI.V (MBTA Communities Multi‑family Overlay District). Previous hearing 9-22-25.
  • OTHER
    motion by keith second by tom to authorize vhb to do the traffic and engineering peer review on rocky hill
    Approved 7-0
  • CONTINUE
    I make a motion that we continue the public hearing on rocky hill uh mbta development to the december 22nd meeting
    Continued 7-0
October 27, 2025PLANNING BOARD
Continued Public Hearing
Continued public hearing on Site Plan under Section XI.V (MBTA Communities Multi-family Overlay District) for the Rocky Hill Development encompassing 265 R, 277 R, 281, 287, 287 R, 287.5 Elm Street. (Previous hearing: 9-22-25)
  • CONTINUE
    Continue the public hearing for Rocky Hill Development to the November 10th meeting of the Planning Board.
    Approved 7-0
September 22, 2025PLANNING BOARD
New Public Hearing
Public hearing for Site Plan review under Section XI.V (MBTA Communities Multi-family Overlay District) for parcels 265 R, 277 R, 281, 287, 287 R, and 287.5 Elm Street (Rocky Hill Development).
  • CONTINUE
    I'll make a motion that we continue this public hearing to Monday, October 27th
    Approved 7-0
March 25, 2024PLANNING BOARD
Presentation
Presentation regarding the MBTA Multi-Family Project affecting 265, 277, 281, 287, 2871/2 Elm St.

Documents on file

SEP 8
2026-08-24 Rocky Hill Site Peer Review 4 and Review 3.pdf
AUG 17
8-17 peer review response supporting materails.pdf
AUG 17
RH Civil-Landscape Plans 8-17-26.pdf
AUG 17
RH Drain Report 8-17-26.pdf
AUG 17
Rocky Hill PR3 -Meeting Notes.pdf
AUG 13
MFOD Waiver Letter 8.12.26.pdf
AUG 6
2026-08-03_Rocky Hill Site Peer Review 3.pdf
JUL 8
RH Drain Report 7-8-26.pdf
JUL 1
MEI Peer Review Response No2 7-1-26.pdf
JUL 1
RH Civil-Landscape Plans 6-29-26.pdf
MAR 25
O and M Manuals 8-11-25.pdf
MAR 25
Peer review attachemnts Geotech and CF figures.pdf
MAR 25
Peer Review Response 3-25-26.pdf
MAR 25
RH Civil Landscpe 3-24-2026.pdf
MAR 25
Rocky Hill Def Sub 3-23-26.pdf
MAR 25
Stormwater Report 3-20-26.pdf
FEB 26
2026-02-25_Rocky Hill Site Peer Review.pdf
FEB 19
Rocky Hill RTC 02.18.26.pdf
FEB 12
Rocky Hill Amesbury MassDOT Section 61 Finding 11.07.25.pdf
FEB 12
Rocky Hill August 2025 FEIR Transportation Component.pdf
FEB 12
Rocky Hill Residences TIA Appendix 11_24.pdf
FEB 12
Rocky Hill transportation peer review.pdf
FEB 12
Rte 110 Improvements FDR August 2025.pdf
JAN 12
Stormwater Report 1-12-26.pdf
DEC 23
RH CIVIL AND LS REV1 12-22-25.pdf
DEC 23
ROCKY HILL-NORTH ARCH 12-02-25.pdf
DEC 23
ROCKY HILL - NORTH ARCH 25_1112.pdf
PDF
DEC 23
ROCKY HILL - SOUTH ARCH - REV 12-18-25.pdf
DEC 23
Stormwater Report 12-8-25.pdf
AUG 14
25_0801-GTA-SitePlanReviewSubmission.pdf
AUG 14
Abutters List.pdf
AUG 14
Form D.pdf
AUG 14
Narrative 8.13.25.rnd (002).pdf
AUG 14
RH Civil and LS Plans 8-11-25.pdf
AUG 14
RH SPR Application.pdf
AUG 14
Rocky Hill Draft Letter of Commitment 07_25.pdf
AUG 14
Rocky Hill Residences TIA 11_24.pdf
AUG 14
ROCKY HILL - SOUTH NEIGHBORHOOD 8-4-25.pdf
AUG 14
Stormwater Report 8-11-25.pdf