WEATHER77° / 58° · CLOUDS ☀ RISE 6:26 AM · SET 6:49 PM ↑ HIGH 5:29 PM · ↓ LOW 11:14 AM
Home / Projects /29 Lake Attitash Road
SPECIAL PERMIT · PLANNING BOARD

29 Lake Attitash Road - Special Permit

pending

Gallery

Auto-selected pages from the source documents. See Documents on file below for the originals.

Project details

What is proposed

Construction of a single‑family residence and associated site work at 29 Lake Attitash Road. The engineering and planning materials submitted show a proposed house foundation footprint of about 1,052 square feet, underground utility connections to the town water and sewer mains in Lake Attitash Road, a small driveway and walkways, and stormwater controls including grassed conveyance, pervious pavers, and a rain garden to treat and infiltrate runoff.

Where and how big

The parcel is roughly 0.25 acres (Tax Map 59, Lot 47) in the R‑20 zoning district and is located within Zone C of the City’s Water Resources Protection Overlay District. The applicant’s memorandum estimates total impervious area of about 980 square feet; the submitted site plans show the 1,052‑square‑foot house roof area plus limited paved surfaces. Access will remain from Lake Attitash Road.

Stormwater, soils and wetlands

A Stormwater Management Report and HydroCAD analyses were submitted showing on‑site treatment and infiltration designed to maintain or reduce peak runoff relative to existing conditions. The rain garden and other measures are modeled with available storage on the order of a few hundred cubic feet (examples in the modeling output show 325 cubic feet in one scenario and staged storage values up to roughly 640–715 cubic feet for larger events). The report’s summarized peak flows show pre‑development peaks of 0.09 cfs (2‑yr), 0.41 cfs (10‑yr) and 1.17 cfs (100‑yr), and post‑development peaks with the proposed BMPs of about 0.09 cfs (2‑yr), 0.25 cfs (10‑yr) and 1.07 cfs (100‑yr).

Three soil probe logs accompany the report; they identify sandy loam conditions (Walpole and Scarboro map units) and a seasonal high groundwater table observed at about 16–18 inches below the ground surface, which informed the proposed infiltration design. A bordering vegetated wetland lies near the northern corner of the lot; the applicant states structures are sited outside the 50‑foot wetland buffer to the greatest extent practicable and notes that if any portion falls between 35–50 feet of the wetland a pile‑supported foundation and Conservation Commission review would be used to limit disturbance.

Status

Complete Special Permit application materials (site plans, stormwater report, soils probes, architectural elevations, and a memorandum in support) were submitted in late 2025. The Planning Board has engaged a stormwater peer review process (city estimate dated March 2026) and the applicant has supplied response materials and revised plans in 2026. The proposal remains under review by the Planning Board as a Special Permit application.

Discussion at meetings

September 14, 2026PLANNING BOARD
Continued Public Hearing
Continued public hearing for a Special Permit under XIV Water Resource Protection District. Applicant requests continuation to October 14, 2026.
  • CONTINUE
    Continue the continued public hearing for 29 Lake Attitash Road to October 14, 2026.
    Approved 7-0
August 10, 2026PLANNING BOARD
Continued Public Hearing
Special Permit application for 29 Lake Attitash Road; applicant requests continuance to 2026-08-24. (Public hearing opened 2025-11-03.)
July 13, 2026PLANNING BOARD
Continued Public Hearing
Continued public hearing (first heard 11-3-25) for a Special Permit at 29 Lake Attitash Road.
  • CONTINUE
    Continue the continued public hearing for 29 Lake Attitash Road to the August 10, 2026 Planning Board meeting.
    Approved 7-0
June 8, 2026PLANNING BOARD
Continued Public Hearing
Special Permit review. (Public hearing opened 11-3-25) Request to continue to July 13, 2026.
May 11, 2026PLANNING BOARD
Continued Public Hearing
Continued public hearing for a Special Permit application at 29 Lake Attitash Road.
  • CONTINUE
    to continue the 29 Lake Attitash Road special permit to the June 8th meeting
    Approved 6-0
April 27, 2026PLANNING BOARD
Continued Public Hearing
Special Permit application; original public hearing 11-3-25.
March 23, 2026PLANNING BOARD
Continued Public Hearing
Request to continue to 2026-04-27. Special Permit application for 29 Lake Attitash Road. Original public hearing date: 2025-11-03.
  • APPROVE
    Authorize staff to engage Stantec to perform a peer review for the application at 29 Lake Attitash Road.
    Approved 6-0
March 9, 2026PLANNING BOARD
Continued Public Hearing
Continued public hearing for a special permit at 29 Lake Attitash Road. Request to continue to March 23, 2026.
  • CONTINUE
    i move to continue 29 lake attach road the special permit here to second march 23rd
    Approved 7-0
February 23, 2026PLANNING BOARD
Continued Public Hearing
Special Permit review; public hearing originally opened 11-3-25.
January 29, 2026PLANNING BOARD
Continued Public Hearing
Continued Special Permit for 29 Lake Attitash Road; application includes a request to continue to 2026-02-23 (original hearing 11-3-25).
  • CONTINUE
    next up is 29 Lake Attitash Road special permit which is also requested to be continued to the 23rd so moved
    Approved 7-0
January 26, 2026PLANNING BOARD
Continued Public Hearing
Continued review for a Special Permit at 29 Lake Attitash Road (previous hearing 11-3-25).
December 22, 2025PLANNING BOARD
Continued Public Hearing
Special Permit review for 29 Lake Attitash Road (public hearing 11-3-25). Request to continue to 1/26/25.
  • CONTINUE
    the applicant requested to continue to the 126th meeting so move second
    Motion passes unanimously seven to zero
November 3, 2025PLANNING BOARD
New Public Hearing
Public hearing for Special Permit application at 29 Lake Attitash Road.
  • CONTINUE
    So I'll make a motion that we continue 29 Lake Attitash special permit to the planning board meeting of December 22nd
    Approved Unanimous

Documents on file