NOTICE OF INTENT · CONSERVATION COMMISSION
I-495 - Notice of Intent
Request for Certificate of Compliance for MassDOT highway work along I-495 Northbound in Amesbury, seeking confirmation of completion under the Order of Conditions.
approved infrastructureenvironmental
PROJECT RENDERING · I-495
AI summary
This request seeks a Certificate of Compliance for work completed under the Order of Conditions associated with MassDOT’s I-495 highway project in Amesbury (Northbound side, Mile Marker 117.1–117.3). The applicant asserts that all conditions of the Order have been satisfactorily met.
Discussion at meetings
Requests for Certificates · Item RCoC 002-1342
Request for Certificate of Compliance for I-495 drainage (continued).
- APPROVEI move that we grant the certificate of compliance for the drainage project.
New Business · Item NOI 002-1342
Notice of Intent from MassDOT (Stedman) for I-495 drainage maintenance (public hearing scheduled).
- APPROVEissue the OOC for NOI 002-1342 I-495 Mass DOT