approve2026-050
approve 2024 dash 0 5 0 as presented and in accordance with the memo from Public Works director
National Grid is granted permission to install underground electric conduits along Elm Street to feed a new pad-mounted transformer and EV charging station at 284 Elm Street, including a 3-phase riser at pole 80-50. The project involves work in a public street and private property, with notices and a hearing completed.
The Amesbury City Council, after a public hearing, approves National Grid's petition to excavate Elm Street and install underground conduits to serve a new pad-mounted transformer on private property and an EV charging station at 284 Elm Street. The conduits are to be located in substantial accordance with the filed plan, with required house connections and notices acknowledged.